CBOC Annual Report 2017-2018

Project List

Measure G Bond Projects as of June 30, 2018

Project NameBudgetExpended
Board Approved
Campus Way-finding Signage$452,360$0
Campus Entry Improvements $595,600$0
Small Capital Improvements $775,000$0
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 3) $1,560,000$0
FFE for Hyman Hall $1,000,000$0
FFE for Building 5$1,000,000$8,075
FFE for Building 9$600,000$66,454
Programming
Parking, Road and Site Improvements$1,814,578$1,391,527
Plaza & Landscape Improvements$1,000,000$268,454
Renovate Building 9$11,059,474$3,554,506
Site Security Systems$1,426,056$463,316
Hyman Hall Renovations$5,301,728$1,493,900
Design
Parking Structures $31,869,985 $26,283,425
Renovate Building 5 $6,439,706 $898,631
Renewable Energy Generation $32,276,950 $31,580,319
FFE for Academic Core Project$7,587,355 $493,822
Construction
Academic Core Buildings $181,385,435 $132,477,180
Newark Site Security Systems $485,000 $98,066
Close Out
Athletic Fields $13,969,388 $13,937,514
Roof Repair/Replacement $1,070,734 $1,002,311
Site Utility Infrastructure Improvements $13,678,885 $13,646,989
Site Lighting Upgrades $677,400 $378,339
Information Technology Infrastructure Upgrades $2,275,000 $2,274,900
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 1) $1,503,031 $1,502,868
Quick Fix: Imminent Failure $4,809,884 $4,791,057
Quick Fix: Safety and Accessibility $2,569,716 $2,557,327
Quick Fix: Way-finding and Landscape $273,423 $267,895
FFE for Athletic Fields $400,000 $398,491
Procurement
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 2) $1,560,000 $951,821
Complete
Bird (Swallow) Environmental Alternatives $283,904 $283,904
Newark Additional Parking (300 spaces) $884,911 $884,911
Newark Greenhouse Project $383,105 $383,105
Energy Efficiency Projects $17,286 $17,286
Uncategorized Projects
Unallocated Interest Earnings $2,861,558 $0
Program Mgmt, Planning and Support $10,404,702 $3,418,997
Contingency
Catastrophic Contingency $5,500,000$0
Program Contingency$2,945,041 $0
Totals:$352,697,196 $245,775,388
View Consolidated Projects