CBOC Annual Report 2021-2022

Project List

Measure G Bond Projects as of June 30, 2022

Project NameBudgetExpended
Construction
Renovate Building 5 $13,713,725$13,194,514
Site Security Systems $1,356,747$919,044
Campus Way-finding Signage $202,441$156,426
Small Capital Improvements $921,560 $789,294
Newark Grounds Office and Equipment Storage Space $127,705 $62,472
FFE for Academic Core Project $1,604,537 $1,050,044
Close Out
Academic Core Buildings $208,120,895 $207,766,049
Hyman Hall Renovations $1,977,894 $1,923,079
Building 4 Renovation $1,233,544 $1,219,118
Newark Site Security Systems $620,762 $619,966
Newark Cashier Window and Security Camera $68,160 $45,302
Renewable Energy Generation $33,661,273 $33,612,414
New Marquee Signs at the Fremont and Newark Campuses $118,602 $103,276
Procurement
Parking, Road and Site Improvements $2,946,385 $2,868,760
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 3) $1,342,485 $249,964
FFE for Building 5 $350,000 $275,385
Complete
Athletic Fields $14,582,415 $14,582,415
Roof Repair/Replacement $1,002,311 $1,002,311
Site Utility Infrastructure Improvements $13,647,495 $13,647,495
Pathways and Irrigation Improvements $337,516 $337,516
Parking Structures $32,848,346 $32,848,346
Renovate Building 9 $3,554,506 $3,554,506
Site Lighting Upgrades $453,686 $453,686
Bird (Swallow) Environmental Alternatives $283,904 $283,904
Newark Additional Parking (300 spaces) $884,911 $884,911
Newark Greenhouse Project $383,105 $383,105
Information Technology Infrastructure Upgrades $2,274,900 $2,274,900
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 1) $1,502,868 $1,502,868
Quick Fix: Imminent Failure $4,791,057 $4,791,057
Quick Fix: Safety and Accessibility $2,557,327 $2,557,327
Quick Fix: Way-finding and Landscape $272,045 $272,045
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 2) $1,558,908 $1,558,908
FFE for Athletic Fields $398,491 $398,491
Energy Efficiency Projects $17,286 $17,286
FFE for Building 9 $66,454 $66,454
Uncategorized Projects
Unallocated Interest Earnings $428,178 $0
Program Mgmt, Planning and Support $4,601,588 $3,785,497
Contingency
Catastrophic Contingency $848,395 $0
Program Contingency $0 $0
Totals:$355,662,409 $350,058,136
View Consolidated Projects