CBOC Annual Report 2022-2023

Featured Projects

Measure G Bond Project Highlights

Renovate Building 5


Budget: $14,599,541
Completion Date: Winter 2023

Repair cafeteria/bookstore/office building to replace outdated infrastructure and to correct failing exterior wall waterproofing.

Portable Utility Connections (Newark Grounds Office and Equipment Storage Space)


Budget: $146,703
Completion Date: Fall 2022

Install an engineered portable office for the Newark Grounds position and a storage building for Newark equipment.

Fremont Flagpoles and Lighting (Site Lighting Upgrades)


Budget: $453,686
Completion Date: Fall 2022

Improve exterior lighting to increase safety while decreasing energy usage for areas outside of the athletic fields, south parking structure, academic core buildings and Proposition 39 projects.