CBOC Annual Report 2011-2012

Project List

Measure A Bond Projects as of June 30, 2012

See the Measure G Bond Project List
Project NameBudgetExpended
Ohlone College Newark Center$108,579,490$108,278,745
Student Support Services$35,915,000$35,651,760
Health & Safety Ed. Projects$15,854,394.82$15,540,190
Bond Planning & Coordination$2,977,677$2,832,005
Unallocated Contingency$3,323.18$0
Totals:$163,329,885$162,302,701