CBOC Annual Report 2011-2012

Featured Projects

Measure A & G Bond Projects as of June 30, 2012

Below Grade Water Intrusion Project

Measure A*
Budget: $1,921,356
Completion Date: October 2012
*Multiple funding sources

Modular Science Building

Measure A
Budget: $2,700,000
Completion Date: October 2012

Picture 1 Picture 2

Renewable Energy Generation

Measure G
Phase 1 Budget: $18,700,000
Total Budget: $30,420,000
Est. Completion Date: April 2013

Quick Fix: Imminent Failure

Measure G
Budget: $5,000,000
Est. Completion Date: December 2013

District Facilities Master Plan

Measure G
Budget: $246,000
Completion Date: May 2012

Site Utility Infrastructure Improvements

Measure G
Budget: $10,400,000
Est. Completion Date: April 2015