CBOC Annual Report 2012-2013

Featured Projects

Measure A & G Bond Project Highlights

Below Grade Water Intrusion Project

Measure A*
Budget: $1,921,356
Completion Date: October 2012
*Multiple funding sources

Modular Science Building

Measure A
Budget: $2,700,000
Completion Date: October 2012

Renewable Energy Generation

Measure G
Total Budget: $30,449,700
Est. Completion Date: April 2013

Quick Fix: Imminent Failure

Measure G
Budget: $5,280,000
Est. Completion Date: December 2013

Academic Core

Measure G
Budget: $98,933,790
Est. Completion Date: June 2018

South Parking Structure

Measure G
Budget: $31,911,750
Est. Completion Date: November 2019

Athletic Fields

Measure G
Budget: $8,223,556
Est. Completion Date: May 2015

Newark Library laptops

Newark Classroom Minipads

Newark Classroom projectors

Instructional Technology - Phase 1

Measure G
Budget: $1,560,000
Est. Completion Date: May 2015