CBOC Annual Report 2013-2014

Project List

Measure G Bond Projects as of June 30, 2014

See the Measure A Bond Project List
Project NameBudgetExpended
Small Capital Improvements$2,275,000$0
Fixtures, Furniture, Equipment for Building 5, 9 and Athletic Fields $2,000,000$0
Site Lighting Upgrades$1,675,000$0
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 2) $1,560,000$0
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 3) $1,560,000$0
Fixtures, Furniture, Equipment for Hyman Hall$1,500,000$0
Newark Soil Remediation$1,372,800$0
Newark Maintenance/Warehouse Building$1,251,250$0
Campus Entry Improvements$795,600$0
Wetland Living/Learning Environment$466,440$0
Campus Way-finding Signage$452,360$0
Hazardous Material Abatement and Removal$411,840$0
Fixtures, Furniture, Equipment (FFE) for the Academic Core Project$9,000,000$137,988
Renovate Building 5$8,936,875$20,000
Renovate Building 9$15,370,663$61,108
Program Management, Planning and Support$15,305,591$1,414,482
Parking Structures$36,959,591$4,053,290
Plaza & Landscape Improvements$7,662,815$268,454
Quick Fix: Imminent Failure$5,471,502$3,986,980
Hyman Hall Renovations$5,274,460$612,831
Parking, Road and Site Improvements$3,797,476$403,516
Roof Repair/Replacement$3,378,062$24,259
Quick Fix: Safety and Accessibility$2,271,894$1,525,923
Quick Fix: Way-Finding and Landscape$1,059,568$114,720
Newark Additional Parking (300 spaces)$1,039,929$266,351
Newark Greenhouse Project$625,724$65,544
Bird (Swallow) Environmental Alternatives$554,584$175,236
Academic Core Buildings$134,274,036$9,506,492
Renewable Energy Generation$31,921,501$18,946,438
Site Utility Infrastructure Improvements$15,320,152$2,889,037
Athletic Fields$12,543,375$506,127
Site Security Systems$1,448,905$105,975
Energy Efficiency Projects$1,027,162$14,356
Information Technology Infrastructure Upgrades$2,275,000$2,226,037
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 1) $1,560,000$1,475,081
Unallocated Interest Earned $802,544 $0
Program Contingency$11,100,845$805,782
Catastrophic Contingency$5,500,000 $0
Totals:$349,802,544$49,606,007
View Consolidated Projects