CBOC Annual Report 2014-2015

Project List

Measure G Bond Projects as of June 30, 2015

Project NameBudgetExpended
Site Lighting Upgrades$1,675,000$0
Hazardous Material Abatement and Removal $411,840$0
Wetland Living/Learning Environment $466,440$0
Campus Way-finding Signage $452,360$0
Campus Entry Improvements $795,600$0
Small Capital Improvements$2,275,000$0
Newark Soil Remediation$1,372,800$0
Newark Maintenance/Warehouse Building$1,251,250$0
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 2)$1,560,000$0
FFE for Building 5, 9 and Athletic Fields
$2,000,000
$0
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 3)
$1,560,000
$0
FFE for Hyman Hall
$1,500,000
$0
Renovate Building 5
$8,938,146 $56,621
FFE for Academic Core Project
$9,000,000 $157,192
Program Mgmt, Planning and Support
$13,655,370 $1,414,482
Plaza & Landscape Improvements
$7,662,815
$268,454
Renovate Building 9
$15,385,587 $491,235
Site Security Systems
$1,450,105 $140,571
Hyman Hall Renovations
$5,301,162 $1,382,426
Energy Efficiency Projects
$1,027,263 $17,286
Athletic Fields
$12,573,008 $1,360,220
Roof Repair/Replacement
$3,382,112 $140,981
Site Utility Infrastructure Improvements
$15,644,005 $12,223,038
Parking, Road and Site Improvements
$3,797,749 $411,372
Parking Structures
$37,649,307 $23,932,053
Bird (Swallow) Environmental Alternatives
$558,016 $274,127
Newark Greenhouse Project
$636,317 $370,841
Renewable Energy Generation
$31,949,396 $19,750,397
Quick Fix: Imminent Failure
$5,492,953 $4,605,230
Quick Fix: Safety and Accessibility
$2,947,896 $2,275,342
Quick Fix: Way-finding and Landscape
$412,031 $185,696
Newark Additional Parking (300 spaces)
$1,061,391 $884,911
Academic Core Buildings $134,719,238 $22,337,967
Information Technology Infrastructure Upgrades
$2,275,000 $2,226,577
Instructional Technology (Computers, LCDS, Flat Screens, etc) - (PH 1)
$1,560,000 $1,493,924
Unallocated Interest Earned $762,560 $0
Program Contingency $11,100,8451,068,266
Catastrophic Contingency$5,500,000 $0
Totals:$349,762,560 $97,469,206