Measures A & G CBOC 2013-2014 Annual Report
CBOC Annual Report 2013-2014
Annual Report
Home Page
Letter from
Committee Chair
Budget, Expenditures
& Audits
Project List
& Details
Featured
Projects
About
Measures A & G
Measure G
Bond Overview
Budget
Expenditures
Audit Information
Measure A
Bond Overview
Budget
Expenditures
Audit Information
Measure G - Budget
as of June 30, 2014
Architectural & Engineering, Oversight, & Other
$52,441,609
Construction & Contingency
$256,847,542
Furniture & Equipment
$20,949,682
Catastrophic Contingency
$5,500,000
Overhead
$13,261,167
Interest Earned
$802,544
Total Budget
$349,802,544