Measure G - Budget
as of June 30, 2015
Architectural & Engineering, Oversight, & Other
$51,355,190
Construction & Contingency
$257,040,769
Furniture & Equipment
$21,345,621
Catastrophic Contingency
$5,500,000
Overhead
$13,758,420
Interest Earned
$762,560
Total Budget
$349,762,560